New electricity connection (domestic meter)

नयाँ विद्युत मिटर जडान

Responsible office

Nepal Electricity Authority distribution centre (DCS) for your area

नेपाल विद्युत प्राधिकरण वितरण केन्द्र

Official website
Who can applyOwners of a house or land who need a new single-phase or three-phase electricity connection; supply is given in the legal owner's name.
Typical timeNEA's published material gives no current time limit. Its last public commitment (Poush 2075) was 7 days for a new single-phase meter, 15 days for three-phase and one month for a TOD meter. News reports (2022) describe delays of months where a pole, line or transformer is needed.
Taxes / chargesNot stated

01 · Before you apply

Essential information

Legal basis

Nepal Electricity Authority Act 2041; Electricity Act 2049 and Electricity Regulations 2050 (Act names not re-verified in this research); NEA consumer tariff and service-rate schedule

Fee information as of

Undated NEA service-rate schedule, linked as current in Oct 2026 (post-Mangsir 2078 tariff)

Source updated

not shown (fee schedule undated; NEA tariff page updated 2026-10-09 AD)

Data confidence

medium

02 · Prepare

Documents you need

Bring original documents together with readable photocopies. Names, dates and record details should match across every document.

  • NEA new customer application form (नयाँ ग्राहक निवेदन फारम) – download from nea.org.np or collect at the distribution centre
  • Photocopy of the owner's citizenship certificate (नागरिकता प्रमाणपत्र)
  • Photocopy of the land ownership certificate (लालपुर्जा / जग्गाधनी प्रमाणपुर्जा)
  • Building approval certificate from the municipality (नक्सा पास / भवन निर्माण इजाजत). NEA's page says 'Building Approval Certificate'; ask whether a completion certificate (निर्माण सम्पन्न प्रमाणपत्र) is also needed
  • Ward office recommendation (वडा सिफारिस)
  • Photograph of the applicant (number and size not published – confirm at the distribution centre)
  • If the applicant is not the registered owner: the document NEA's English page calls a 'resignation letter' (probably राजीनामा or the owner's consent, मञ्जुरीनामा) – confirm at the distribution centre

03 · At the office

Step-by-step process

  1. 1

    Find the NEA distribution centre (वितरण केन्द्र) that serves your area. Contacts are at nea.org.np/contact-information-of-dcs.

  2. 2

    Get the application form: download it from nea.org.np or collect it at the centre. Three-phase applicants can apply fully online at crm.nea.org.np/new-connection.

  3. 3

    Submit the form and documents before any service line is drawn, and pay the application fee.

  4. 4

    NEA estimates the cost of connecting your premises (pole, line, transformer if needed). Pay the service charge in that estimate.

  5. 5

    Finish the house wiring. NEA inspects it before supply starts: the first inspection is free, your wiring contractor must be present, and re-inspections may be charged.

  6. 6

    Pay the meter installation charge. NEA installs the meter and connects supply in the legal owner's name.

  7. 7

    Keep every receipt. If NEA cannot connect you immediately, ask the centre to give the expected date in writing; complaints go to NEA's line 1150.

04 · Cost

Fees and charges

Application form (domestic)

Rs 200 for other (non-domestic) customers

Rs 100

Meter installation charge – 5A single-phase domestic

Rs 100

Meter installation charge – 15A

Rs 150

Meter installation charge – 30A

Rs 300

Meter installation charge – 60A

Rs 500

Meter installation charge – three-phase domestic

Other customers: up to 10 kVA Rs 1,000; above 10 kVA Rs 1,500; TOD meter Rs 1,500

Rs 1,000

Fuse service

Rs 100 single-phase / Rs 200 three-phase

Service charge for line, pole or transformer work

Based on the estimated cost of connecting your premises

Varies – per NEA's site estimate

Meter price, security deposit (धरौटी) or demand charge

NEA's online fee schedule lists none of these; ask the distribution centre for a written estimate

Not published — confirm at the office

Wiring re-inspection

First inspection is free

Not published — confirm at the office

Monthly minimum charge after connection (for reference, 0–20 units)

5A users of up to 20 units pay no energy charge; higher consumption blocks cost Rs 6.50–11 per unit

5A Rs 30; 15A Rs 50; 30A Rs 75; 60A Rs 125

06 · Read carefully

Important notes

  • Supply is given only in the legal owner's name. When buying a property, make sure past electricity bills are cleared.
  • Apply before any line is drawn: NEA says documents must be submitted before taking electricity lines.
  • NEA installs the transformer for loads up to 100 kVA; only customers above 100 kVA may install their own (Onlinekhabar, 2022).
  • Load changes on an existing meter: increases were made free, and reductions cost Rs 300 single-phase / Rs 500 three-phase (Onlinekhabar, Mangsir 2078). Confirm current rates.
  • NEA's fee schedule is undated, and the PDF text was partly garbled, so amounts should be checked at the counter.
  • Office hours: 9:00–17:00 (Magh 16–Kartik 15) and 9:00–16:00 (Kartik 16–Magh 15). NEA main office: 01-4153051, [email protected].

07 · Where to go

Office information

Address

Central Office, Durbarmarg, Kathmandu

Office hours

Mon-Fri; winter (Kartik 16 - Magh 15) 09:00-16:00; summer (Magh 16 - Kartik 15) 09:00-17:00 (as shown on site)

Toll free

1150 (no-light / power outage hotline)